CONNECTICUT ยท THRESHOLDS & STATUTES
The dollar lines Connecticut procurement law draws.
The figures that run Connecticut public purchasing: the DAS state lines ($10K small purchase, quotes to $50K, advertised competitive bids on CTsource at $50K+), the 25% SBE set-aside goal (CGS 4a-60g), the prevailing-wage lines ($100K remodeling / $1M new construction, CGS 31-53), and the honest note that towns set their own lines because county government was abolished in 1960. This page is informational, not legal advice.
CGS Ch. 58 / DAS policy
Small purchase line (state goods and services)
$10,000
At or under this line, state agencies buy directly without a competitive process. Anything larger moves through DAS-standard competition on CTsource.
For vendors: under $10K is the relationship band; a CTsource registration still matters for visibility.
portal.ct.gov/dasCGS Ch. 58 / DAS policy
Open-market band (quotes)
$50,000
Between $10,000 and $50,000 the agency collects at least three open-market quotes. At $50,000 and over, competitive bids are advertised and posted on CTsource for at least five days.
For vendors: $10K-$50K is quote-driven; $50K+ is the advertised CTsource lane.
portal.ct.gov/das/procurement-programs-and-services/ctsourceCGS 4a-60g
Small business set-aside goal (SBE, with MBE sub-goal)
25%
Connecticut's supplier-diversity program is one of the strongest in the region: 25% of state contract value is set aside for certified SBEs, and 25% of the set-aside is aimed at MBEs. Certification runs through DAS Supplier Diversity.
For vendors: SBE/MBE certification through DAS materially improves access to state work.
portal.ct.gov/dasCGS 31-53
Prevailing wage thresholds (public works)
$100,000
Public works remodeling at or over $100,000 and new construction at or over $1,000,000 carry Connecticut prevailing-wage obligations administered by CTDOL. The new-construction line was raised from $400,000 to $1,000,000 by PA 23-35 effective October 1, 2023.
For contractors: check whether the project is remodeling or new construction before pricing labor.
www.cga.ct.gov/current/pub/chap_557.htmTown charters and ordinances
No county government: towns set their own lines
Connecticut abolished county government in 1960; the eight legacy counties in our dataset are geographic references only (the 2024 Census gazetteer now uses nine planning regions). Local purchasing runs through the 169 towns and cities, each with its own charter lines. There is no uniform municipal threshold statute.
For vendors: treat each town as its own market; the local explorer links the largest town per legacy county with verification badges.
portal.ct.gov/das/procurement-programs-and-services/ctsourceStructural fact: county government abolished 1960; dataset note honest about legacy counties vs. 2024 planning regions.
CGS 49-41
Payment bonds (Little Miller)
Connecticut's Little Miller provision (CGS 49-41) requires payment bonds on public works construction contracts.
For contractors: line up surety capacity before bidding public work.
www.cga.ct.gov/current/pub/chap_058.htm
Where these portals live: verification-labeled Connecticut procurement sources and the 8-county local explorer.